Preliminaries Estimator: P&G Cost Estimate for a Project
Estimate preliminaries and general costs including site staff, temporary facilities, equipment, utilities, and site overhead based on project duration and value.
Last updated: January 2026
Indicative prices as of January 2026 — not a quotation. Replace default rates with current supplier quotes.
Total P&G Cost
1,727,000
AED
P&G Percentage
17.27%
of contract value
FINANCIAL DISCLAIMER
This calculator provides INDICATIVE FIGURES for reference purposes only.
Important:
1. Results are based on standard formulas and user-provided inputs. Actual contractual amounts may differ based on specific contract terms and conditions.
Embed this calculator on your site
Paste this snippet into your page. The embedded calculator is free to use and links back to this page.
About This Calculator
The Preliminaries & General (P&G) Estimator helps contractors and quantity surveyors calculate site overhead costs for construction projects across the UAE and Gulf. Estimate costs for site staff, temporary facilities (offices, stores, toilets), plant and equipment, utilities, insurance, and other indirect costs based on project duration and contract value. Essential for accurate tender pricing and project budgeting.
Formula
Site staff = sum of (count × monthly cost) × duration in months
Site setup = sum of one-off setup costs (taken in month 1)
Running costs = sum of monthly running costs × duration in months
Insurance = contract value × insurance rate %
Contingency = (staff + setup + running costs + insurance) × contingency %
Total P&G = staff + setup + running costs + insurance + contingency; P&G % = total ÷ contract value × 100
Worked example
Inputs
- Contract value 10,000,000 AED; duration 18 months
- Staff per month: 1 project manager 25,000; 2 site engineers at 15,000; 1 QA/QC engineer 12,000
- Setup (one-off): site office 50,000; temporary facilities 30,000
- Running per month: utilities 5,000; security 8,000
- Insurance 0.5% of contract value; contingency 10%
Steps
- Staff per month: 25,000 + 2 × 15,000 + 12,000 = 67,000; over 18 months: 1,206,000
- Setup: 50,000 + 30,000 = 80,000
- Running: (5,000 + 8,000) × 18 = 234,000
- Insurance: 0.5% × 10,000,000 = 50,000
- Subtotal: 1,206,000 + 80,000 + 234,000 + 50,000 = 1,570,000
- Contingency: 10% × 1,570,000 = 157,000; total P&G = 1,727,000
- P&G as a share of contract value: 1,727,000 ÷ 10,000,000 = 17.27%
Result: Total P&G of 1,727,000 AED, or 17.27% of the contract value, for these illustrative inputs.
Assumptions and limits
- All staff, setup and running costs are your own inputs. The values shown by default are placeholders for illustration, not salaries, prices or market rates.
- Every staff and running cost line runs for the full duration. Staff who join late or leave early, mobilisation phasing and time-related items that taper off are not modelled.
- Insurance is a flat percentage of the contract value. Contingency is applied to everything above it.
- The project type selection does not change the calculation.
- The tool does not classify items to any measurement standard or tender format. Contractors, projects and contracts differ in what they treat as P&G, so align the items with your tender documents.
- Duration is taken as a whole number of months and capped at 600. The result needs a contract value and duration above zero.
When to Use This Calculator
- Preparing tender submissions with accurate preliminaries pricing
- Budgeting site setup and running costs for new projects
- Comparing P&G costs across different project durations
- Negotiating preliminaries lump sums with clients
- Calculating monthly site overhead for cash flow projections
How to Use This Calculator
Enter Project Details
Input contract value, duration in months, and insurance and contingency percentages.
Add Site Staff
Add site staff with their roles, numbers and monthly cost.
Add Setup Costs
Add one-off site setup costs such as temporary offices, stores and mobilisation.
Add Running Costs
Add monthly running costs such as utilities, transport and site services.
Review P&G Summary
Get a detailed breakdown and the percentage of contract value.
Typical Scenarios in UAE & Gulf Projects
Main contractor prepares tender for 40-storey residential tower with 30-month program. P&G Estimator calculates site team costs (PM, 4 engineers, QS, safety), tower crane rental, temporary offices, and utilities totaling 12% of contract value.
Civil contractor estimates preliminaries for 50km road project across remote desert terrain. Tool accounts for extended camp facilities, generator power, water tankering, and additional supervision staff for multiple work fronts.
Frequently Asked Questions
What percentage should P&G be of contract value?
Preliminaries and general (P&G) as a share of contract value depends on the project type, duration, site location and the staff and facilities the project needs, so there is no single rate. Build it up from your own site establishment, supervision and facilities costs, and compare the resulting percentage with your own past projects.
Are preliminaries time-related or fixed?
P&G costs are a mix of both. Site staff, equipment rental, and utilities are time-related (monthly). Mobilization, temporary buildings, and insurance are typically fixed or partially fixed. The estimator categorizes costs accordingly for extension of time claims.
How do I price P&G for variation negotiations?
Use the monthly rate breakdown from the estimator to calculate additional preliminaries for extended durations. FIDIC contracts typically entitle contractors to prolongation costs for employer-caused delays, calculated from the P&G schedule of rates.
Last Updated: January 2026
Standards Reference: RICS NRM 2 Preliminaries Classification, AACE Cost Estimate Classification