Manpower Planning Calculator: Man-Days and Crew Size by Trade

Calculate labor requirements by trade based on scope and productivity rates. Generates man-day estimates, trade durations and peak workforce.

Last updated: January 2026

Project Settings
Trade Scope Items
Trade #1

Leave blank to use default: 2.5

Leave blank to use default: 6

Trade #2

Leave blank to use default: 12

Leave blank to use default: 3

Total Man-Days

283

Peak Workforce

9

Duration

34 days

Total Man-Days

283

Peak Workers

9

Avg. Workers

8.3

Trade Breakdown
Concrete Work200 man-days(6 workers × 34 days)
Masonry/Blockwork83.3 man-days(3 workers × 28 days)
Productivity Analysis
Concrete Work2.5 m³/worker/dayQty: 500 m³
Masonry/Blockwork12 m²/worker/dayQty: 1,000 m²

Notes:

  • Man-days = Scope Quantity ÷ Productivity Rate
  • Duration = Man-days ÷ (Crew Size × Shift Factor)
  • Shift factor adjusts for hours: 8h ÷ 8h = 1.00
  • Peak workforce assumes all trades work simultaneously
  • Add overtime or weekend work by increasing shift hours
Your results
Email me this calculation
Leave your email and the Arkan team will send you this calculation. The calculator stays free and needs no sign-up.

We use your email to send this calculation. See our Privacy Policy.

ESTIMATION NOTICE

This calculator provides APPROXIMATE QUANTITIES for budgeting and planning purposes.

Please note:

• Results include standard wastage factors but actual waste may vary based on site conditions, workmanship, and material quality.

Embed this calculator on your site

Paste this snippet into your page. The embedded calculator is free to use and links back to this page.

About This Calculator

The Manpower Planning Calculator helps project managers and contractors estimate labor requirements by trade for construction projects across the UAE and Gulf. Calculate man-day estimates, peak workforce needs, and trade durations based on scope quantities and indicative productivity rates. Essential for tender pricing, mobilization planning, and labor camp sizing in Gulf construction.

Formula

Man-days = scope quantity ÷ productivity (output per worker per day)

Shift factor = shift hours ÷ 8

Duration (days) = man-days ÷ (crew size × shift factor), rounded up to whole days

Total man-days = sum of the trade man-days

Peak workforce = sum of all crew sizes (every trade is assumed to work at the same time)

Project duration = the longest single trade duration

Average workforce = total man-days ÷ project duration

Worked example

Concrete and blockwork, default productivity

Inputs

  • Concrete: 500 m³, default productivity 2.5 m³ per worker per day, default crew 6
  • Masonry/blockwork: 1,000 m², default productivity 12 m² per worker per day, default crew 3
  • 8-hour shift (shift factor 1.0)

Steps

  1. Concrete man-days = 500 ÷ 2.5 = 200; duration = 200 ÷ (6 × 1.0) = 33.3, rounded up to 34 days
  2. Masonry man-days = 1,000 ÷ 12 = 83.3; duration = 83.3 ÷ (3 × 1.0) = 27.8, rounded up to 28 days
  3. Total man-days = 200 + 83.3 = 283
  4. Peak workforce = 6 + 3 = 9 workers
  5. Project duration = the longer trade = 34 days
  6. Average workforce = 283.3 ÷ 34 = 8.3 workers

Result: About 283 man-days, a peak of 9 workers and 34 days for the longest trade.

Assumptions and limits

  • The default productivity rates and crew sizes are indicative values built into the calculator, not published norms. Replace them with your own site records where you have them.
  • Productivity is entered per worker per 8-hour day. Changing the shift length scales the duration in proportion and does not model overtime fatigue.
  • Trades are assumed to start together and run in parallel, so the peak workforce is the sum of the crews. Sequencing between trades is not considered.
  • The available working days input is not used to cap the result, so compare the duration against it yourself.

When to Use This Calculator

  • Estimating labor costs during tender preparation
  • Planning workforce mobilization and demobilization
  • Sizing labor camps and accommodation requirements
  • Generating resource S-curves for project planning
  • Coordinating with subcontractors on labor allocation

How to Use This Calculator

1

Enter Scope Quantities

Input quantities for major work items (concrete m³, formwork m², rebar tonnes, etc.).

2

Set Productivity Rates

Enter or use default productivity rates for each trade (adjusted for Gulf conditions).

3

Specify Duration

Input project duration to calculate peak manning requirements.

4

Adjust for Factors

Apply factors for overtime, shift work, weather productivity loss, and learning curves.

5

Review Results

Get man-days and duration by trade, total man-days and peak workforce.

Typical Scenarios in UAE & Gulf Projects

High-Rise Frame in Business Bay

A contractor sizes the frame gangs for a tower: 45,000 m³ of concrete, 4,500 t of rebar and 120,000 m² of formwork. At the tool's indicative rates (2.5 m³, 0.5 t and 8 m² per man-day) that is 18,000 + 9,000 + 15,000 = 42,000 man-days. With crews of 30 concrete workers, 15 steel fixers and 25 carpenters, each trade takes 600 working days, a combined peak of 70 workers on these three trades. Supervision and other trades are added separately.

Checking a Subcontractor Resource Plan

A main contractor enters a subcontractor's scope quantities and proposed crew sizes to check whether the implied durations fit the programme. Where a trade's duration exceeds the available working days, the crew size or productivity assumption needs to change.

Frequently Asked Questions

What productivity rates should I use for UAE construction?

Indicative rates only (not from a published source; calibrate with your own records): concrete placement 15-20 m³/gang/day, formwork erection 8-12 m²/carpenter/day, rebar fixing about 0.4-0.6 t/fixer/day (the tool default is 0.5 t/man-day), blockwork 35-50 blocks/mason/day. Summer months (June-August) reduce rates by 30-40% for outdoor work.

How do I account for indirect labor?

Indirect staff (site engineers, safety officers, QA/QC, stores and logistics, security, camp management) add to the direct labour count. The share depends on project complexity and the supervision your contract and client require, so build it up from your own staffing plan rather than a fixed percentage.

What's the typical labor camp sizing formula?

Camp capacity = peak workforce plus an allowance for rotation and leave, plus space for dining, recreation and medical facilities. The allowance and the area per person come from your own planning assumptions and the accommodation standards that apply to your project. Allow time for visa processing when planning mobilization.

Last Updated: January 2026

Standards Reference: CIOB Code of Practice for Project Management, RSMeans Productivity Data

Do this inside Arkan

A calculator gives you one number. Arkan keeps the quantities, inspections and payment requests for the whole project in one place, in English and Arabic.

Arkan screen: schedule

Need More Than Calculators?

Arkan brings all your construction management together: BOQ tracking, payment certificates, document management, scheduling, and more. All integrated. All in one place.