S-Curve Generator
Generate project S-curves for cash flow and progress planning. Supports early start, late start, and bell curve distributions with interactive charts and data export.
AED 50,000,000
Standard S-curve with peak in middle
| Month | Monthly | Cumulative | % |
|---|---|---|---|
| Month 1 | AED 961,988 | AED 961,988 | 1.9% |
| Month 2 | 2.1M | 3.1M | 6.1% |
| Month 3 | 3.9M | 6.9M | 13.8% |
| Month 4 | 6.0M | 12.9M | 25.8% |
| Month 5 | 7.7M | 20.6M | 41.2% |
| Month 6 | 8.4M | 29.0M | 58.1% |
| Month 7 | 7.7M | 36.8M | 73.5% |
| Month 8 | 6.0M | 42.7M | 85.4% |
| Month 9 | 3.9M | 46.6M | 93.1% |
| Month 10 | 2.1M | 48.7M | 97.3% |
| Month 11 | AED 961,988 | 49.6M | 99.3% |
| Month 12 | AED 370,236 | 50.0M | 100.0% |
Early Start (Front-loaded)
Higher mobilization costs, faster ramp-up
Late Start (Back-loaded)
Delayed mobilization, back-loaded finishing works
Linear
Constant rate of expenditure throughout project
Bell Curve (Standard S)
Typical construction profile with peak at midpoint
Duration
12
Total Value
50.0M
Peak Month
Month 6
Cumulative planned value over project duration
Planned monthly expenditure
Average Monthly
4.2M
Peak Monthly Value
8.4M
50% Progress At
Month 6
Final Value
50.0M
Notes:
- S-curve represents planned value baseline
- Compare actual progress against this curve for variance analysis
- Early/Late start affects cash flow timing
- Bell curve is typical for standard construction projects
- Use for earned value management (EVM) baseline
REFERENCE INFORMATION
This tool provides standard reference data compiled from industry sources.
Note:
• Data is provided for quick reference and may not reflect the most current standards or specifications.