Electrical Load Calculator: Maximum Demand and Main Breaker Size

Calculate total connected load, maximum demand, and electrical sizing requirements. Recommends main breaker size, cable sizing, and transformer capacity.

Last updated: January 2026

System Settings

Demand factor: 0.6x

Fixed Loads

Estimated at 180W per outlet with 30% diversity

Appliances
Appliance #1

Leave blank for default: 2000W

Appliance #2

Leave blank for default: 2500W

Connected Load

16.6 kW

Max Demand

10.0 kW

Main Breaker

80A

Connected Load

16.6 kW

Maximum Demand

10.0 kW

(11.7 kVA)

Electrical Sizing
Main Breaker Size80Amps
Recommended Cable25mm²
Appliance Breakdown
Split AC Unit (×3)6.0 kWDemand: 3.6 kW
Water Heater (×2)5.0 kWDemand: 3.0 kW
Fixed Load Summary
Lighting Load2.0kW
Central HVAC0.0kW
Socket Outlets20 outlets(3.6 kW)

Notes:

  • Maximum demand applies one demand factor for the usage type to the total connected load
  • Main breaker sized at 80% loading capacity
  • Cable sizing based on current carrying capacity
  • Transformer recommended when demand exceeds 50 kVA
  • Power factor assumed at 0.85 for kVA calculation
Your results
Email me this calculation
Leave your email and phone number and the Arkan team will send you this calculation. The calculator stays free and needs no sign-up.

We use your email and phone number to send this calculation and follow up on it. See our Privacy Policy.

DISCLAIMER

This calculator provides ESTIMATES for preliminary planning purposes. Results are based on standard assumptions and may not reflect your specific project conditions.

By using this tool, you acknowledge that:

1. All calculations are approximate and based on typical industry standards and assumptions.

Embed this calculator on your site

Paste this snippet into your page. The embedded calculator is free to use and links back to this page.

About This Calculator

This Electrical Load Calculator helps MEP engineers estimate building electrical requirements per IEC and local utility standards. Calculate total connected load, apply demand factors for different load types, determine maximum demand, and size main electrical distribution equipment. Essential for coordinating with DEWA, ADDC, SEWA, and other Gulf utility providers during building permit applications.

Formula

Appliance load = wattage × quantity (default wattage used if you leave it blank)

Socket load = number of outlets × 180 W

Connected load = appliances + lighting + central HVAC + sockets

Maximum demand = connected load × demand factor for the usage type (residential 0.6, commercial 0.7, industrial 0.8)

kVA = maximum demand ÷ 0.85 (power factor)

Design current: single phase I = P ÷ (230 × 0.85); three phase I = P ÷ (√3 × 400 × 0.85)

Main breaker = next standard size at or above I ÷ 0.8

Worked example

Villa with split ACs and water heaters on a 230 V supply

Inputs

  • Residential, 230 V single phase
  • 3 split AC units (2,000 W each) and 2 water heaters (2,500 W each)
  • Lighting 2,000 W, no central HVAC, 20 socket outlets

Steps

  1. Appliances = 3 × 2,000 + 2 × 2,500 = 11,000 W; sockets = 20 × 180 = 3,600 W
  2. Connected load = 11,000 + 2,000 + 0 + 3,600 = 16,600 W
  3. Maximum demand = 16,600 × 0.6 = 9,960 W, which is 11.7 kVA at 0.85 power factor
  4. Design current = 9,960 ÷ (230 × 0.85) = 50.9 A
  5. Breaker size needed = 50.9 ÷ 0.8 = 63.7 A, so the next standard size is 80 A
  6. The 80 A breaker maps to a 25mm² cable in the built-in table

Result: Connected load 16,600 W, maximum demand 9,960 W (11.7 kVA), 80 A main breaker, 25mm² cable.

Assumptions and limits

  • A single demand factor for the selected usage type is applied once to the whole connected load; the per-appliance factors shown in the list are not used in the total.
  • Socket outlets are counted at a flat 180 W each.
  • Power factor is fixed at 0.85 and the supply is 50 Hz, 230 V single phase or 400 V three phase.
  • The cable size comes from a short current-carrying table keyed to the breaker rating. Voltage drop, grouping, ambient temperature, installation method and short-circuit duty are not checked.
  • A transformer size is suggested only when demand exceeds 50 kVA, with a 20% margin, rounded up to a standard size.
  • Use it for early sizing only; final design must be done and approved by a qualified electrical engineer against the applicable regulations and the utility's requirements.

When to Use This Calculator

  • Calculating electrical loads for new building designs
  • Sizing main switchboards and distribution boards
  • Determining transformer capacity requirements
  • Preparing load schedules for utility applications
  • Verifying electrical capacity for building additions

How to Use This Calculator

1

Enter connected loads

Input lighting, power, HVAC, and equipment loads in kW or kVA

2

Apply demand factors

Select appropriate demand factors based on load type and codes

3

Calculate maximum demand

Tool computes total maximum demand with diversity

4

Size main equipment

Get recommended main breaker, cable, and transformer sizes

5

Review load schedule

Export formatted load schedule for utility submission

Typical Scenarios in UAE & Gulf Projects

Dubai Office Tower

30-floor commercial tower with 500kW lighting, 800kW small power, 2000kW HVAC, and 300kW lifts. Calculator applies demand factors (0.9 lighting, 0.6 power, 0.85 HVAC) yielding 2,650kVA maximum demand at 0.85 PF. Recommends 2x1600kVA transformers with 30% future capacity.

Abu Dhabi Villa Compound

20-villa residential compound, each villa with 65kW connected load. Using ADDC residential demand factors (0.4-0.6), calculator determines 800kVA compound transformer plus individual villa DBs at 100A each. Includes EV charger provisions per Estidama requirements.

Frequently Asked Questions

What demand factors should I use for UAE buildings?

Demand factors depend on the utility authority and the load type, so use the factors in the guidelines that apply to your project (for example the authority that will supply the building) or those given by the electrical design consultant. The demand factor in the calculator is an input you can change.

How do I size the main transformer?

Calculate maximum demand in kVA (kW ÷ power factor), add 20-30% for future growth, then select next standard transformer size (500, 1000, 1500, 2000 kVA). For high-rises, multiple transformers improve reliability. Redundancy (for example N+1) is a design and client decision for critical facilities; check the utility's current requirements for your project.

What is the difference between connected load and maximum demand?

Connected load is the sum of all installed equipment ratings (nameplate kW/kVA). Maximum demand is the actual peak load expected considering that not all equipment runs simultaneously. Demand factors convert connected load to maximum demand based on building type and usage patterns; take them from the utility guidelines or your electrical design consultant.

Last Updated: January 2026

Standards Reference: IEC 60364, DEWA/ADDC/SEWA Regulations, BS 7671

Do this inside Arkan

A calculator gives you one number. Arkan keeps the quantities, inspections and payment requests for the whole project in one place, in English and Arabic.

Arkan screen: inspections

Need More Than Calculators?

Arkan brings all your construction management together: BOQ tracking, payment certificates, document management, scheduling, and more. All integrated. All in one place.

We Value Your Privacy

We use cookies to enhance your browsing experience, analyze site traffic, and personalize content. By clicking "Accept All", you consent to our use of cookies. Read our Privacy Policy

If you allow Marketing Cookies, OpenAI Ads measures accepted demo requests and relates them to advertising using browser and page signals. When enabled, automatic matching may use hashed contact details. You can withdraw permission in Cookie settings. Your enquiry will still be sent if you reject marketing cookies.