Cut and Fill Calculator: Earthwork Volumes
Calculate earthwork cut and fill volumes from cross-sections (average end area). Compare cut and fill in bank m³ using shrinkage, and get import/export in bank and loose m³ for haulage.
Last updated: January 2026
Take it from your geotechnical report or compaction trials. 1 bank m³ of cut gives this many m³ of compacted fill.
Take it from your geotechnical report or site records. Used for truck (loose) volumes.
1,850
bank m³ (in-situ)
Makes 1,572.5 m³ compacted fill
2,400
compacted m³
Needs 2,823.53 m³ bank volume of soil
973.53 bank m³
Import: 1,119.56 m³ loose to haul
| Stations | Cut (bank m³) | Fill (compacted m³) | Cumulative (bank m³) |
|---|---|---|---|
| 0–20 m | 650 | 50 | +591.18 |
| 20–40 m | 700 | 200 | +1,055.88 |
| 40–60 m | 400 | 500 | +867.65 |
| 60–80 m | 100 | 850 | -32.35 |
| 80–100 m | 0 | 800 | -973.53 |
Cut is measured in bank (in-situ) m³ and fill in compacted m³. The balance compares both in bank m³: fill ÷ shrinkage factor = bank m³ needed.
Import/export is given in bank m³ and in loose m³ (× bulking factor) for truck haulage, assuming imported material has the same factors as the site soil.
IMPORTANT DISCLAIMER
This calculator provides PRELIMINARY ESTIMATES ONLY and is intended for planning and budgeting purposes. Results should NOT be used for final structural design or construction without verification by a licensed Professional Engineer (PE) or Chartered Engineer (CEng).
By using this tool, you acknowledge that:
1. All calculations are indicative and may not account for site-specific conditions, load combinations, or local code requirements.
Embed this calculator on your site
Paste this snippet into your page. The embedded calculator is free to use and links back to this page.
About This Calculator
The Cut & Fill Calculator helps civil engineers and earthworks contractors estimate grading quantities for construction sites across the UAE and Gulf. Enter cut and fill areas at each cross-section station; the calculator uses the average end area method to get cut volume in bank (in-situ) m³ and fill volume in compacted m³. It converts the fill to the bank m³ of soil needed using the shrinkage factor, so cut and fill are compared in the same state, then reports import or export in bank m³ and in loose m³ (using the bulking factor) for truck haulage.
Formula
Between two stations: volume = average of the two end areas × distance between them
Cut volume is in bank (in-situ) m³; fill volume is in compacted m³
Fill in bank m³ = compacted fill ÷ shrinkage factor
Net = total cut (bank) − total fill (bank)
Loose haul volume = net bank volume × bulking factor
Cumulative (mass haul ordinate) = running sum of [cut − fill in bank m³]
Worked example
Inputs
- Stations 0, 20, 40, 60, 80, 100 m
- Cut areas: 25, 40, 30, 10, 0, 0 m²
- Fill areas: 0, 5, 15, 35, 50, 30 m²
- Shrinkage factor 0.85 (compacted ÷ bank), bulking factor 1.15 (loose ÷ bank)
Steps
- Stations 0 to 20 m: average cut (25 + 40) ÷ 2 = 32.5 m² × 20 m = 650 m³; average fill (0 + 5) ÷ 2 = 2.5 m² × 20 m = 50 m³.
- The other four sections give cut volumes of 700, 400, 100 and 0 m³ and fill volumes of 200, 500, 850 and 800 m³.
- Total cut = 650 + 700 + 400 + 100 + 0 = 1,850 bank m³. Total fill = 50 + 200 + 500 + 850 + 800 = 2,400 compacted m³.
- The cut would make 1,850 × 0.85 = 1,572.5 compacted m³ of fill.
- Fill in bank volume = 2,400 ÷ 0.85 = 2,823.53 bank m³.
- Net = 1,850 − 2,823.53 = −973.53, so the balance is excess fill and 973.53 bank m³ must be imported.
- Loose volume to haul in = 973.53 × 1.15 = 1,119.56 m³.
Result: Excess fill: import 973.53 bank m³, about 1,119.56 loose m³ to haul.
Assumptions and limits
- Volumes use the average end area method, which is usually adequate for gently varying ground but can over- or under-estimate where the sections change sharply.
- Cut and fill areas at each station are inputs. The calculator does not measure them from a drawing or a terrain model.
- Cut is treated as bank volume and fill as compacted volume, and the balance compares both in bank volume using the shrinkage factor. A single shrinkage and bulking factor applies to all soil on the job.
- Imported material is assumed to have the same shrinkage and bulking factors as the site soil.
- Topsoil stripping, rock, unsuitable material and swell or shrink that changes along the route are not modelled.
- The typical factor ranges shown beside the inputs (shrinkage 0.80 to 0.95, bulking 1.10 to 1.30) are rough guides; use values from your geotechnical report.
When to Use This Calculator
- Planning site grading for new construction projects
- Estimating earthwork quantities for tender submissions
- Calculating material import/export requirements
- Optimizing cut-fill balance to minimize haulage costs
- Verifying subcontractor earthwork claims
How to Use This Calculator
Enter Cross-Sections
Enter the chainage (station) of each cross-section with its cut area and fill area in m², from your survey or design sections.
Set Shrinkage Factor
Shrinkage = compacted ÷ bank volume (typically 0.80-0.95). It converts compacted fill to the bank m³ of soil needed.
Set Bulking Factor
Bulking = loose ÷ bank volume (typically 1.10-1.30). It converts the import or export to loose m³ for truck haulage.
Review Balance
Get cut (bank m³), fill (compacted m³ and bank m³ needed), the net import or export, and the cumulative mass haul ordinates.
Typical Scenarios in UAE & Gulf Projects
A 100 m road section with cross-sections every 20 m: cut areas 25, 40, 30, 10, 0, 0 m² and fill areas 0, 5, 15, 35, 50, 30 m². The calculator gives 1,850 bank m³ of cut and 2,400 compacted m³ of fill. With a shrinkage factor of 0.85 the fill needs 2,823.5 bank m³, so the cut covers only part of it and 973.5 bank m³ must be imported, which is 1,119.6 loose m³ of haulage at a bulking factor of 1.15. Comparing loose cut with compacted fill instead would understate the import.
A subcontractor claims import quantities measured in trucks (loose m³). Convert them back to bank m³ by dividing by the bulking factor, and compare with the bank m³ shortfall from the calculator, so both are in the same state before certifying.
Frequently Asked Questions
What are bank, loose and compacted volumes?
Bank (in-situ) volume is soil in the ground before excavation. Loose volume is the same soil after excavation, larger because of bulking (loose = bank × bulking factor). Compacted volume is the soil placed and compacted in the fill, usually smaller than bank (compacted = bank × shrinkage factor). Cut and fill must be compared in the same state; this calculator uses bank m³.
What are typical shrink/swell factors?
Indicative values: sand and gravel bulk 10-15% when excavated and shrink 5-15% when compacted; clay bulks 20-30% and shrinks 10-20%; rock bulks 40-60% and usually does not shrink below bank volume. Use the factors from your geotechnical report and compaction trials.
How accurate is the average end area method?
Accuracy depends on section spacing and how much the ground changes between sections. For gently varying ground, 20-25 m spacing is common; use closer sections where the ground or design changes quickly. The method slightly overestimates where one section is in full cut and the next in full fill.
Last Updated: January 2026
Standards Reference: Average end area method; bank/loose/compacted volume conversions per standard earthworks practice
