Free Monthly Progress Report Template
A generic monthly progress report for construction projects. Compare planned and actual progress, summarise the financial position, list key activities, the look-ahead and open issues. Excel and PDF, English and Arabic.
Download the template
Preview
A preview of the template layout. The files have more blank rows and, in Excel, working formulas and drop-downs.
Monthly Progress Report
- Project
- Report no.
- Reporting period
- Prepared by
- Date
- Contract completion date
Overall progress
| Planned cumulative progress (%) | |
|---|---|
| Actual cumulative progress (%) | |
| Variance (actual minus planned, %) | = |
Financial summary
| Original contract value | |
|---|---|
| Approved variations | |
| Revised contract value | = |
| Certified to date | |
| Certified to date (% of revised value) | = |
Key activities
| Activity / work package | Planned start | Planned finish | Forecast finish | Planned % | Actual % | Variance % | Comments |
|---|---|---|---|---|---|---|---|
| = calculated | |||||||
| = calculated | |||||||
| = calculated | |||||||
| ... (10 rows in the file) | |||||||
Look-ahead (next period)
| Planned activity | Start | Finish | Prerequisites / information needed |
|---|---|---|---|
| ... (6 rows in the file) | |||
Issues and risks
| Issue / risk | Owner | Action | Due date | Status |
|---|---|---|---|---|
| ... (6 rows in the file) | ||||
What is included
- Header: project, report number, reporting period, author, date and contract completion date
- Overall progress: planned and actual percentage with the variance calculated
- Financial summary: contract value, variations, revised value, certified to date and percentage certified
- Key activities with planned, forecast and percentage progress; look-ahead; issues and risks
How to fill it in
- Take planned and actual percentages from the same baseline programme and update.
- Enter the contract value, approved variations and the amount certified to date.
- List key activities with planned and forecast dates and planned and actual progress.
- Add the look-ahead for the next period, including the information you need from others.
- Record open issues and risks with an owner, action and due date. Attach photographs and the latest programme.
Do this without spreadsheets: Arkan project dashboards
Arkan's project dashboard shows these figures live from the project's data instead of a monthly rebuild.
- Financial KPIs, cost variations and an estimated projection
- Cumulative progress curve and schedule and activities KPIs
- Data comes from the project's schedule, BOQ and payment records