Material Submittals and the Submittal Workflow in Construction

Arkan Team
Updated 10 min read

What Are Construction Submittals?

Construction submittals are documents submitted by contractors to consultants and clients for review and approval before work proceeds. They verify that proposed materials, equipment, and methods comply with contract requirements and design intent.

Related: the glossary entry for a material submittal, RFI vs submittal vs ball-in-court and the Submittals module.

For UAE projects, efficient submittal management is critical—delays in submittal approvals ripple through procurement, installation, and ultimately project completion.

Types of Submittals

Shop Drawings

Detailed fabrication drawings prepared by contractors or suppliers showing:

  • Exact dimensions and specifications
  • Installation details
  • Connections and interfaces
  • Material specifications

Examples: Structural steel shop drawings, MEP coordination drawings, curtain wall details

Material Submittals

Documentation for proposed materials including:

  • Product data sheets
  • Technical specifications
  • Certificates of compliance
  • Samples (physical or digital)

Examples: Concrete mix designs, paint color selections, flooring materials

Equipment Submittals

Information about mechanical and electrical equipment:

  • Equipment specifications
  • Performance data
  • Installation requirements
  • Maintenance documentation

Examples: HVAC units, elevator systems, generators

Method Statements

Procedures explaining how work will be executed:

  • Sequence of activities
  • Safety considerations
  • Quality control measures
  • Resources required

Examples: Concrete pouring methodology, lifting operations, waterproofing application

The Submittal Approval Chain

UAE Project Hierarchy

Typical UAE submittal workflow involves multiple approval levels:

Level 1: Contractor Review Internal QA/QC review before external submission

Level 2: Subconsultant Review Specialist consultant (structural engineer, MEP engineer) reviews relevant submittals

Level 3: Main Consultant Review Lead consultant (typically architect) provides final technical review

Level 4: Developer/Client Review (optional) Some clients require visibility or approval for certain submittals

Approval Statuses

Common submittal response codes (the exact codes are set by each contract or consultant):

A - Approved: Work may proceed as submitted

B - Approved as Noted: Work may proceed with minor modifications noted

C - Revise and Resubmit: Significant issues require resubmission before work proceeds

D - Rejected: Submittal not acceptable; major revision or alternative required

Workflow Example: Shop Drawing Submittal

Step 1: Preparation (Contractor)

Specialist subcontractor prepares shop drawings:

  • Structural steel fabricator develops detailed connection drawings
  • Internal review ensures compliance with contract drawings
  • Submittal package compiled with cover sheet

Step 2: Contractor Submission

Main contractor:

  • Reviews submittal for completeness
  • Assigns submittal number (e.g., SUB-STR-001-R0)
  • Submits to consultant with transmittal

Step 3: Subconsultant Review

Structural engineer:

  • Reviews against structural design drawings
  • Checks calculations and specifications
  • Provides comments or approval
  • Returns to main consultant

Step 4: Main Consultant Review

Architect/lead consultant:

  • Reviews subconsultant comments
  • Checks coordination with other disciplines
  • Issues final response to contractor

Step 5: Response Handling

If approved: Contractor proceeds to fabrication

If revise and resubmit:

  • Contractor addresses comments
  • Resubmits as revision (SUB-STR-001-R1)
  • Process repeats until approved

Want to see this in Arkan?

Book a demo and we will walk through it on a sample project.

Common Submittal Bottlenecks

Incomplete Submissions

Problem: Submittals missing required information returned without review

Solution: Submittal checklists ensuring completeness before submission

Unclear Routing

Problem: Submittals sent to wrong reviewer, bouncing between parties

Solution: Clear workflow definition by submittal type and discipline

Long Review Cycles

Problem: Submittals sitting in review queues for weeks

Solution: Response time tracking with escalation for overdue items

Lost in Email

Problem: Submittals buried in email, status unknown

Solution: Centralized submittal tracking system replacing email workflows

Version Confusion

Problem: Reviews based on superseded versions

Solution: Identify the file revision and keep the response that applies to it. In Arkan, file version history and formal submittal review are separate records.

Submittal Response Time Benchmarks

Review periods come from the signed contract, specification and agreed project procedure. Record the applicable period for each submittal type, work backwards from procurement or installation needs, and allow for a revised submission where required. Do not treat a generic number as a contractual commitment or a software delivery promise.

Use the actual submission, response and resubmission dates to identify where a request waited. A late item alone does not establish the cause of delay or a contractual entitlement.

Best Practices for UAE Submittals

1. Establish Submittal Schedule

Create a submittal register early showing:

  • All required submittals
  • Required submission dates (based on procurement/installation needs)
  • Expected review duration
  • Critical path items

2. Define Approval Matrix

Document which reviewers approve which submittal types:

DisciplineSubconsultantMain ConsultantDeveloper
StructuralStructural EngArchitectNo
MEPMEP ConsultantArchitectNo
Finishes-ArchitectYes
FF&EInterior DesignerArchitectYes

3. Implement Submittal Software

Replace email-based workflows with dedicated systems providing:

  • Automatic routing to correct reviewers
  • Status visibility for all parties
  • Response time tracking
  • Revision management
  • Audit trails

4. Hold Submittal Coordination Meetings

Weekly meetings to:

  • Review overdue submittals
  • Escalate blocked items
  • Coordinate multi-discipline reviews
  • Align submittal and procurement schedules

5. Track and Report Metrics

Monitor submittal health:

  • Submittals pending by duration
  • Average response time by reviewer
  • First-time approval rate
  • Revision cycles per submittal

Impact of Delayed Submittals

Procurement Delays

Materials cannot be ordered until submittals are approved. Long review cycles push back material delivery dates.

Installation Delays

Work cannot proceed without approved shop drawings. Crews wait or move to other areas.

Schedule Impact

Submittal delays compound through the project:

  • 2-week submittal delay
    • 4-week procurement lead time
    • Installation sequence dependencies
  • = Multi-week schedule impact

Financial Consequences

Delays lead to:

  • Extension of time claims
  • Acceleration costs
  • Resource inefficiencies
  • Potential liquidated damages

How Arkan Streamlines Submittals

Arkan's submittal module addresses common workflow challenges:

Configurable workflows: Define approval chains by submittal type and discipline matching UAE project hierarchies.

Automatic routing: Submitted requests follow the configured workflow sequence and groups. Check the project configuration and assigned review actions during your demonstration.

Status visibility: Submittal dashboards, KPI cards and a submittal log let the team inspect recorded statuses. Their usefulness depends on the completeness of the project records.

Submittal plans and follow-ups: Build submittal plans (including from your Primavera schedule) and track late and pending items on the follow-up dashboard.

Escalation and delegation: Stalled workflow items can be escalated, and approvers can delegate when they're away.

Workflow history: Workflow history shows the approval chain, timestamps and user actions so the team can trace the recorded review.

See how Arkan manages submittals → Book a Demo

Conclusion

A clear submittal workflow gives the team defined review responsibilities, recorded statuses and response dates. Project outcomes also depend on complete submissions, reviewer action and the actual schedule dependencies.

For a project with several review parties, compare the documented software workflow with the records and responsibilities in your current process.

Ready to streamline your submittal workflow?

Request Demo | See All Features

Frequently asked questions

What is a construction submittal?

A construction submittal is a package of proposed materials, equipment, drawings or methods sent for review before the relevant work proceeds. Reviewers compare it with the project requirements and record their response.

Why are submittals important?

Submittals give reviewers a record of what is proposed, the supporting documents and their response before procurement or installation. Approval records support coordination; they do not replace the contractor's responsibilities or the project's acceptance procedures.

How long should submittal review take?

Use the review period in the signed contract, specification and agreed project procedure. Record the due date and route for each submittal type, and allow for any required resubmission. There is no universal review period for every project.

What happens if a submittal is returned for revision?

Read the reviewer comments, update the relevant documents, identify the revision and resubmit through the agreed workflow. Keep the earlier submission and response available so reviewers can trace what changed.

How does Arkan record a submitted document request?

The documented Submittals workflow checks required attachments and the workflow action before Send Request. The request then becomes read-only, with workflow history showing the approval chain, timestamps and user actions. See the published Submittals help guide for the full steps.

#submittals#construction workflow#approvals#shop drawings#UAE construction
Share:

Explore Related Arkan Features

See how Arkan solves these challenges in our platform.

See it in Arkan

Explore Submittals, or book a demo to see how it works on your own workflow.

We Value Your Privacy

We use cookies to enhance your browsing experience, analyze site traffic, and personalize content. By clicking "Accept All", you consent to our use of cookies. Read our Privacy Policy

If you allow Marketing Cookies, OpenAI Ads measures accepted demo requests and relates them to advertising using browser and page signals. When enabled, automatic matching may use hashed contact details. You can withdraw permission in Cookie settings. Your enquiry will still be sent if you reject marketing cookies.