What Are Construction Submittals?
Construction submittals are documents submitted by contractors to consultants and clients for review and approval before work proceeds. They verify that proposed materials, equipment, and methods comply with contract requirements and design intent.
For UAE projects, efficient submittal management is critical—delays in submittal approvals ripple through procurement, installation, and ultimately project completion.
Types of Submittals
Shop Drawings
Detailed fabrication drawings prepared by contractors or suppliers showing:
- Exact dimensions and specifications
- Installation details
- Connections and interfaces
- Material specifications
Examples: Structural steel shop drawings, MEP coordination drawings, curtain wall details
Material Submittals
Documentation for proposed materials including:
- Product data sheets
- Technical specifications
- Certificates of compliance
- Samples (physical or digital)
Examples: Concrete mix designs, paint color selections, flooring materials
Equipment Submittals
Information about mechanical and electrical equipment:
- Equipment specifications
- Performance data
- Installation requirements
- Maintenance documentation
Examples: HVAC units, elevator systems, generators
Method Statements
Procedures explaining how work will be executed:
- Sequence of activities
- Safety considerations
- Quality control measures
- Resources required
Examples: Concrete pouring methodology, lifting operations, waterproofing application
The Submittal Approval Chain
UAE Project Hierarchy
Typical UAE submittal workflow involves multiple approval levels:
Level 1: Contractor Review Internal QA/QC review before external submission
Level 2: Subconsultant Review Specialist consultant (structural engineer, MEP engineer) reviews relevant submittals
Level 3: Main Consultant Review Lead consultant (typically architect) provides final technical review
Level 4: Developer/Client Review (optional) Some clients require visibility or approval for certain submittals
Approval Statuses
Standard submittal response codes:
A - Approved: Work may proceed as submitted
B - Approved as Noted: Work may proceed with minor modifications noted
C - Revise and Resubmit: Significant issues require resubmission before work proceeds
D - Rejected: Submittal not acceptable; major revision or alternative required
Workflow Example: Shop Drawing Submittal
Step 1: Preparation (Contractor)
Specialist subcontractor prepares shop drawings:
- Structural steel fabricator develops detailed connection drawings
- Internal review ensures compliance with contract drawings
- Submittal package compiled with cover sheet
Step 2: Contractor Submission
Main contractor:
- Reviews submittal for completeness
- Assigns submittal number (e.g., SUB-STR-001-R0)
- Submits to consultant with transmittal
Step 3: Subconsultant Review
Structural engineer:
- Reviews against structural design drawings
- Checks calculations and specifications
- Provides comments or approval
- Returns to main consultant
Step 4: Main Consultant Review
Architect/lead consultant:
- Reviews subconsultant comments
- Checks coordination with other disciplines
- Issues final response to contractor
Step 5: Response Handling
If approved: Contractor proceeds to fabrication
If revise and resubmit:
- Contractor addresses comments
- Resubmits as revision (SUB-STR-001-R1)
- Process repeats until approved
Common Submittal Bottlenecks
Incomplete Submissions
Problem: Submittals missing required information returned without review
Solution: Submittal checklists ensuring completeness before submission
Unclear Routing
Problem: Submittals sent to wrong reviewer, bouncing between parties
Solution: Clear workflow definition by submittal type and discipline
Long Review Cycles
Problem: Submittals sitting in review queues for weeks
Solution: Response time tracking with escalation for overdue items
Lost in Email
Problem: Submittals buried in email, status unknown
Solution: Centralized submittal tracking system replacing email workflows
Version Confusion
Problem: Reviews based on superseded versions
Solution: Automatic version control with clear current/superseded status
Submittal Response Time Benchmarks
Industry standards for response times:
| Submittal Type | Target Response |
|---|---|
| Shop drawings | 10-14 working days |
| Material submittals | 7-10 working days |
| Method statements | 5-7 working days |
| Simple product data | 3-5 working days |
UAE reality: Many projects exceed these targets due to workflow inefficiencies.
Best Practices for UAE Submittals
1. Establish Submittal Schedule
Create a submittal register early showing:
- All required submittals
- Required submission dates (based on procurement/installation needs)
- Expected review duration
- Critical path items
2. Define Approval Matrix
Document which reviewers approve which submittal types:
| Discipline | Subconsultant | Main Consultant | Developer |
|---|---|---|---|
| Structural | Structural Eng | Architect | No |
| MEP | MEP Consultant | Architect | No |
| Finishes | - | Architect | Yes |
| FF&E | Interior Designer | Architect | Yes |
3. Implement Submittal Software
Replace email-based workflows with dedicated systems providing:
- Automatic routing to correct reviewers
- Status visibility for all parties
- Response time tracking
- Revision management
- Audit trails
4. Hold Submittal Coordination Meetings
Weekly meetings to:
- Review overdue submittals
- Escalate blocked items
- Coordinate multi-discipline reviews
- Align submittal and procurement schedules
5. Track and Report Metrics
Monitor submittal health:
- Submittals pending by duration
- Average response time by reviewer
- First-time approval rate
- Revision cycles per submittal
Impact of Delayed Submittals
Procurement Delays
Materials cannot be ordered until submittals are approved. Long review cycles push back material delivery dates.
Installation Delays
Work cannot proceed without approved shop drawings. Crews wait or move to other areas.
Schedule Impact
Submittal delays compound through the project:
- 2-week submittal delay
-
- 4-week procurement lead time
-
- Installation sequence dependencies
- = Multi-week schedule impact
Financial Consequences
Delays lead to:
- Extension of time claims
- Acceleration costs
- Resource inefficiencies
- Potential liquidated damages
How Arkan Streamlines Submittals
Arkan's submittal module addresses common workflow challenges:
Configurable workflows: Define approval chains by submittal type and discipline matching UAE project hierarchies.
Automatic routing: Submittals route to correct reviewers without manual forwarding.
Status visibility: All parties see real-time submittal status—no more status inquiry emails.
Response tracking: Dashboard highlighting overdue items with automatic reminder notifications.
Revision management: Clear tracking of revisions with full history and comparison tools.
Complete audit trails: Every action logged for claims documentation and dispute resolution.
See how Arkan manages submittals → Book a Demo
Frequently Asked Questions
What is a construction submittal?
A construction submittal is documentation submitted by contractors for review and approval before work proceeds. Submittals verify that proposed materials, equipment, and methods comply with contract requirements.
Why are submittals important?
Submittals ensure quality and compliance. They allow consultants to verify contractor proposals before irreversible work proceeds. They also create documentation for project records.
How long should submittal review take?
Industry standards suggest 7-14 working days depending on complexity. Complex shop drawings may need longer. Simple product data should be faster.
What happens if a submittal is rejected?
Rejected submittals require revision and resubmission. The contractor addresses reviewer comments, updates the submission, and routes it through the approval chain again.
How can I speed up submittal approvals?
Key strategies: submit complete documentation, use submittal software for efficient routing, track response times, escalate overdue items, and hold regular coordination meetings.
Conclusion
Submittal management significantly impacts project success. Efficient workflows—with clear routing, status visibility, and response tracking—reduce delays and keep projects on schedule.
For UAE projects with complex approval hierarchies, dedicated submittal software delivers substantial value over email-based processes.