What Are Construction Submittals?
Construction submittals are documents submitted by contractors to consultants and clients for review and approval before work proceeds. They verify that proposed materials, equipment, and methods comply with contract requirements and design intent.
Related: the glossary entry for a material submittal, RFI vs submittal vs ball-in-court and the Submittals module.
For UAE projects, efficient submittal management is critical—delays in submittal approvals ripple through procurement, installation, and ultimately project completion.
Types of Submittals
Shop Drawings
Detailed fabrication drawings prepared by contractors or suppliers showing:
- Exact dimensions and specifications
- Installation details
- Connections and interfaces
- Material specifications
Examples: Structural steel shop drawings, MEP coordination drawings, curtain wall details
Material Submittals
Documentation for proposed materials including:
- Product data sheets
- Technical specifications
- Certificates of compliance
- Samples (physical or digital)
Examples: Concrete mix designs, paint color selections, flooring materials
Equipment Submittals
Information about mechanical and electrical equipment:
- Equipment specifications
- Performance data
- Installation requirements
- Maintenance documentation
Examples: HVAC units, elevator systems, generators
Method Statements
Procedures explaining how work will be executed:
- Sequence of activities
- Safety considerations
- Quality control measures
- Resources required
Examples: Concrete pouring methodology, lifting operations, waterproofing application
The Submittal Approval Chain
UAE Project Hierarchy
Typical UAE submittal workflow involves multiple approval levels:
Level 1: Contractor Review Internal QA/QC review before external submission
Level 2: Subconsultant Review Specialist consultant (structural engineer, MEP engineer) reviews relevant submittals
Level 3: Main Consultant Review Lead consultant (typically architect) provides final technical review
Level 4: Developer/Client Review (optional) Some clients require visibility or approval for certain submittals
Approval Statuses
Common submittal response codes (the exact codes are set by each contract or consultant):
A - Approved: Work may proceed as submitted
B - Approved as Noted: Work may proceed with minor modifications noted
C - Revise and Resubmit: Significant issues require resubmission before work proceeds
D - Rejected: Submittal not acceptable; major revision or alternative required
Workflow Example: Shop Drawing Submittal
Step 1: Preparation (Contractor)
Specialist subcontractor prepares shop drawings:
- Structural steel fabricator develops detailed connection drawings
- Internal review ensures compliance with contract drawings
- Submittal package compiled with cover sheet
Step 2: Contractor Submission
Main contractor:
- Reviews submittal for completeness
- Assigns submittal number (e.g., SUB-STR-001-R0)
- Submits to consultant with transmittal
Step 3: Subconsultant Review
Structural engineer:
- Reviews against structural design drawings
- Checks calculations and specifications
- Provides comments or approval
- Returns to main consultant
Step 4: Main Consultant Review
Architect/lead consultant:
- Reviews subconsultant comments
- Checks coordination with other disciplines
- Issues final response to contractor
Step 5: Response Handling
If approved: Contractor proceeds to fabrication
If revise and resubmit:
- Contractor addresses comments
- Resubmits as revision (SUB-STR-001-R1)
- Process repeats until approved
Common Submittal Bottlenecks
Incomplete Submissions
Problem: Submittals missing required information returned without review
Solution: Submittal checklists ensuring completeness before submission
Unclear Routing
Problem: Submittals sent to wrong reviewer, bouncing between parties
Solution: Clear workflow definition by submittal type and discipline
Long Review Cycles
Problem: Submittals sitting in review queues for weeks
Solution: Response time tracking with escalation for overdue items
Lost in Email
Problem: Submittals buried in email, status unknown
Solution: Centralized submittal tracking system replacing email workflows
Version Confusion
Problem: Reviews based on superseded versions
Solution: Identify the file revision and keep the response that applies to it. In Arkan, file version history and formal submittal review are separate records.
Submittal Response Time Benchmarks
Review periods come from the signed contract, specification and agreed project procedure. Record the applicable period for each submittal type, work backwards from procurement or installation needs, and allow for a revised submission where required. Do not treat a generic number as a contractual commitment or a software delivery promise.
Use the actual submission, response and resubmission dates to identify where a request waited. A late item alone does not establish the cause of delay or a contractual entitlement.
Best Practices for UAE Submittals
1. Establish Submittal Schedule
Create a submittal register early showing:
- All required submittals
- Required submission dates (based on procurement/installation needs)
- Expected review duration
- Critical path items
2. Define Approval Matrix
Document which reviewers approve which submittal types:
| Discipline | Subconsultant | Main Consultant | Developer |
|---|---|---|---|
| Structural | Structural Eng | Architect | No |
| MEP | MEP Consultant | Architect | No |
| Finishes | - | Architect | Yes |
| FF&E | Interior Designer | Architect | Yes |
3. Implement Submittal Software
Replace email-based workflows with dedicated systems providing:
- Automatic routing to correct reviewers
- Status visibility for all parties
- Response time tracking
- Revision management
- Audit trails
4. Hold Submittal Coordination Meetings
Weekly meetings to:
- Review overdue submittals
- Escalate blocked items
- Coordinate multi-discipline reviews
- Align submittal and procurement schedules
5. Track and Report Metrics
Monitor submittal health:
- Submittals pending by duration
- Average response time by reviewer
- First-time approval rate
- Revision cycles per submittal
Impact of Delayed Submittals
Procurement Delays
Materials cannot be ordered until submittals are approved. Long review cycles push back material delivery dates.
Installation Delays
Work cannot proceed without approved shop drawings. Crews wait or move to other areas.
Schedule Impact
Submittal delays compound through the project:
- 2-week submittal delay
-
- 4-week procurement lead time
-
- Installation sequence dependencies
- = Multi-week schedule impact
Financial Consequences
Delays lead to:
- Extension of time claims
- Acceleration costs
- Resource inefficiencies
- Potential liquidated damages
How Arkan Streamlines Submittals
Arkan's submittal module addresses common workflow challenges:
Configurable workflows: Define approval chains by submittal type and discipline matching UAE project hierarchies.
Automatic routing: Submitted requests follow the configured workflow sequence and groups. Check the project configuration and assigned review actions during your demonstration.
Status visibility: Submittal dashboards, KPI cards and a submittal log let the team inspect recorded statuses. Their usefulness depends on the completeness of the project records.
Submittal plans and follow-ups: Build submittal plans (including from your Primavera schedule) and track late and pending items on the follow-up dashboard.
Escalation and delegation: Stalled workflow items can be escalated, and approvers can delegate when they're away.
Workflow history: Workflow history shows the approval chain, timestamps and user actions so the team can trace the recorded review.
See how Arkan manages submittals → Book a Demo
Conclusion
A clear submittal workflow gives the team defined review responsibilities, recorded statuses and response dates. Project outcomes also depend on complete submissions, reviewer action and the actual schedule dependencies.
For a project with several review parties, compare the documented software workflow with the records and responsibilities in your current process.