العربية

Liquidated Damages Calculator: Delay Damages and Cap

Calculate liquidated damages for project delays. Considers LD rates, approved EOT, caps, and generates comprehensive delay penalty assessments.

Last updated: January 2026

Contract Details

AED 50,000,000

Extension of Time already approved

Liquidated Damages Rate

AED 50,000 per day

LD Cap / Limit

Max LD: AED 5,000,000

Delay Days

60days

LD Amount

AED 3,000,000

LD %

6.00%

Liquidated Damages Calculation

Delay Period

60 days

(Gross: 90 days - EOT: 30 days)

LD Amount

AED 3,000,000

6.00% of contract value

LD Rate Breakdown
Daily RateAED 50,000/day
Weekly RateAED 350,000/week
Monthly Rate (approx)AED 1,500,000/month
Payment Summary
Contract ValueAED 50,000,000
Less: Liquidated Damages- AED 3,000,000
Net PayableAED 47,000,000
Project Timeline
OriginalExtendedActual
2024-12-31+30d 2025-03-31

Notes:

  • Whether an LD clause is enforceable depends on the contract and the governing law: take legal advice
  • EOT claims should be assessed before applying LD
  • Review contract for specific LD provisions
  • Any cap on LD is set by your contract: enter it in the cap field
Your results
Email me this calculation
Leave your email and phone number and the Arkan team will send you this calculation. The calculator stays free and needs no sign-up.

We use your email and phone number to send this calculation and follow up on it. See our Privacy Policy.

FINANCIAL DISCLAIMER

This calculator provides INDICATIVE FIGURES for reference purposes only.

Important:

1. Results are based on standard formulas and user-provided inputs. Actual contractual amounts may differ based on specific contract terms and conditions.

Embed this calculator on your site

Paste this snippet into your page. The embedded calculator is free to use and links back to this page.

About This Calculator

This Liquidated Damages (LD) Calculator helps contractors and employers calculate delay penalties per contract terms. Determine LD exposure considering daily rates, approved EOT, contractual caps, and sectional completion provisions. Essential for financial planning and dispute avoidance in UAE and Gulf construction contracts where LD clauses are standard practice.

Formula

Gross delay = actual completion − original completion (days, not below 0)

Delay period = actual completion − (original completion + approved EOT days), not below 0

Daily rate = rate per day; or weekly rate ÷ 7; or (rate % ÷ 100) × contract value

LD before cap = daily rate × delay period

Cap = cap % × contract value, or a fixed amount; LD = lower of LD before cap and the cap

Contract value less LD = contract value − LD

Worked example

Daily LD rate with a 10% cap

Inputs

  • Contract value 20,000,000
  • LD rate 50,000 per day
  • Original completion 31 Dec 2024; actual completion 31 Mar 2025
  • Approved EOT 30 days; cap 10% of contract value

Steps

  1. Gross delay: 31 Dec 2024 to 31 Mar 2025 = 90 days
  2. Delay period after EOT: 90 − 30 = 60 days
  3. LD before cap: 60 × 50,000 = 3,000,000
  4. Cap: 10% × 20,000,000 = 2,000,000, which is lower, so the cap applies
  5. LD = 2,000,000, which is 10% of the contract value
  6. Contract value less LD: 20,000,000 − 2,000,000 = 18,000,000

Result: LD of 2,000,000 (the 3,000,000 before the cap is limited by the cap); contract value less LD is 18,000,000.

Assumptions and limits

  • The rate, the cap and whether LD applies at all come from your contract. The figures in this example are illustrative, not typical or standard terms.
  • The percentage rate option is read as a percentage of the contract value per day. If your contract states a different basis, use a daily amount instead.
  • Only the approved EOT days are deducted. Sectional completion, partial possession, different rates for different sections, and notice requirements are not modelled.
  • Contract value less LD is shown to illustrate the deduction. It is not the amount payable, because other payments and deductions are not modelled.
  • Whether the clause is enforceable, whether it is a genuine pre-estimate of loss, and any rules on penalties depend on the contract and applicable law and are not assessed here.
  • Amounts are shown in AED. A negative or zero delay gives zero LD.
  • Any entitlement, deduction or payment depends on the actual contract terms and the governing law. This calculator is an arithmetic aid, not legal or contractual advice.

When to Use This Calculator

  • Calculating potential LD exposure during project execution
  • Verifying employer's LD deduction calculations
  • Assessing financial risk of project delays
  • Negotiating LD caps in contract negotiations
  • Preparing for dispute resolution on LD claims

How to Use This Calculator

1

Enter contract details

Input contract value, completion date, and sectional milestones if any

2

Define LD terms

Enter the daily LD rate and the maximum cap stated in your contract

3

Input approved EOT

Add any approved extension of time to adjust completion date

4

Enter actual completion

Input actual or forecast completion date

5

Review LD calculation

View delay days, LD amount, and cap application

Typical Scenarios in UAE & Gulf Projects

Dubai Residential Tower Delay

120M AED contract with 0.1% daily LD (120,000 AED/day), 10% cap. Project delayed 95 days beyond adjusted completion date. Calculator shows: 95 × 120,000 = 11.4M AED, but capped at 12M (10%). Net LD = 11.4M AED deducted from final payment.

Sectional Completion Abu Dhabi Mall

Mixed-use development with separate LD for retail (0.05%/day) and residential (0.08%/day) sections. Calculator applies 45-day retail delay (LD: 2.25M) and 20-day residential delay (LD: 1.6M) separately, totaling 3.85M AED against combined 8M cap.

Frequently Asked Questions

How is the LD rate set?

The LD rate and the cap are stated in your contract (for FIDIC forms, in the Particular Conditions or Contract Data), and the calculator uses the figures you enter. Rates should represent a genuine pre-estimate of loss; whether a given rate can be enforced is a legal question, so take legal advice on a specific contract.

Can LD be challenged if they exceed actual losses?

Under UAE Civil Code (Article 390), courts can reduce LD if they are excessive compared to actual loss suffered. However, the burden is on the contractor to prove the employer suffered less damage. Courts may also reduce LD if partial performance provided some benefit to the employer.

How do sectional completion provisions affect LD?

Sectional completion allows employer to take over parts of the works while LD continues for uncompleted sections. Each section should have its own completion date, LD rate, and cap. If a completed section is used, the employer may have reduced claim for losses on that portion. Check contract carefully for sectional provisions.

Last Updated: January 2026

Standards Reference: FIDIC 1999 Red Book Sub-Clause 8.7 Delay Damages (2017 edition Sub-Clause 8.8), UAE Civil Code Article 390

Do this inside Arkan

A calculator gives you one number. Arkan keeps the quantities, inspections and payment requests for the whole project in one place, in English and Arabic.

Arkan screen: dashboards

Need More Than Calculators?

Arkan brings all your construction management together: BOQ tracking, payment certificates, document management, scheduling, and more. All integrated. All in one place.

We Value Your Privacy

We use cookies to enhance your browsing experience, analyze site traffic, and personalize content. By clicking "Accept All", you consent to our use of cookies. Read our Privacy Policy

If you allow Marketing Cookies, OpenAI Ads measures accepted demo requests and relates them to advertising using browser and page signals. When enabled, automatic matching may use hashed contact details. You can withdraw permission in Cookie settings. Your enquiry will still be sent if you reject marketing cookies.