Free Construction Calculators & Tools/Liquidated Damages Calculator

Liquidated Damages Calculator

Calculate liquidated damages for project delays. Considers LD rates, approved EOT, caps, and generates comprehensive delay penalty assessments.

Contract Details

AED 50,000,000

Extension of Time already approved

Liquidated Damages Rate

AED 50,000 per day

LD Cap / Limit

Max LD: AED 5,000,000

Typical LD Rates (UAE)
Project TypeDaily RateTypical Cap
Residential Villa0.05% - 0.1%10%
Commercial Building0.1% - 0.15%10%
Infrastructure0.05% - 0.1%10-15%
Government Projects0.1%10%

Delay Days

60

LD Amount

AED 3,000,000

LD %

6.00%

Liquidated Damages Calculation

Delay Period

60 days

(Gross: 90 days - EOT: 30 days)

LD Amount

AED 3,000,000

6.00% of contract value

LD Rate Breakdown
Daily RateAED 50,000/day
Weekly RateAED 350,000/week
Monthly Rate (approx)AED 1,500,000/month
Payment Summary
Contract ValueAED 50,000,000
Less: Liquidated Damages- AED 3,000,000
Net PayableAED 47,000,000
Project Timeline
OriginalExtendedActual
2024-12-31+30d2025-03-31

Notes:

  • LD must be a genuine pre-estimate of loss to be enforceable
  • Penalty clauses may be void under UAE law
  • EOT claims should be assessed before applying LD
  • Review contract for specific LD provisions
  • LD cap typically ranges from 5-15% of contract value
Save Your Calculation
Get a professional PDF report of this calculation, plus access to templates and additional resources.

FINANCIAL DISCLAIMER

This calculator provides INDICATIVE FIGURES for reference purposes only.

Important:

1. Results are based on standard formulas and user-provided inputs. Actual contractual amounts may differ based on specific contract terms and conditions.

About This Calculator

This Liquidated Damages (LD) Calculator helps contractors and employers calculate delay penalties per contract terms. Determine LD exposure considering daily rates, approved EOT, contractual caps, and sectional completion provisions. Essential for financial planning and dispute avoidance in UAE and Gulf construction contracts where LD clauses are standard practice.

When to Use This Calculator

  • Calculating potential LD exposure during project execution
  • Verifying employer's LD deduction calculations
  • Assessing financial risk of project delays
  • Negotiating LD caps in contract negotiations
  • Preparing for dispute resolution on LD claims

How to Use This Calculator

1

Enter contract details

Input contract value, completion date, and sectional milestones if any

2

Define LD terms

Enter daily LD rate and maximum cap (typically 5-10% of contract value)

3

Input approved EOT

Add any approved extension of time to adjust completion date

4

Enter actual completion

Input actual or forecast completion date

5

Review LD calculation

View delay days, LD amount, and cap application

Typical Scenarios in UAE & Gulf Projects

Dubai Residential Tower Delay

120M AED contract with 0.1% daily LD (120,000 AED/day), 10% cap. Project delayed 95 days beyond adjusted completion date. Calculator shows: 95 × 120,000 = 11.4M AED, but capped at 12M (10%). Net LD = 11.4M AED deducted from final payment.

Sectional Completion Abu Dhabi Mall

Mixed-use development with separate LD for retail (0.05%/day) and residential (0.08%/day) sections. Calculator applies 45-day retail delay (LD: 2.25M) and 20-day residential delay (LD: 1.6M) separately, totaling 3.85M AED against combined 8M cap.

Frequently Asked Questions

Take Your Calculations Further

This calculator reflects the logic built into Arkan's construction management platform.

Last Updated: January 2026

Standards Reference: FIDIC Conditions of Contract Clause 8.7, UAE Civil Code Article 390

Need More Than Calculators?

Arkan brings all your construction management together: BOQ tracking, payment certificates, document management, scheduling, and more. All integrated. All in one place.