Critical Path Calculator
Calculate critical path, float times, and project duration from activity networks. Identify critical activities and scheduling flexibility.
Add activities to calculate the critical path
REFERENCE INFORMATION
This tool provides standard reference data compiled from industry sources.
Note:
• Data is provided for quick reference and may not reflect the most current standards or specifications.
About This Calculator
The Critical Path Calculator helps project planners and schedulers perform Critical Path Method (CPM) analysis for construction projects across the UAE and Gulf. Calculate the critical path, total float and project duration from an activity network with finish-to-start links. Identify critical activities that drive project completion and activities with scheduling flexibility.
When to Use This Calculator
- Identifying activities that control project duration
- Calculating float to understand scheduling flexibility
- Analyzing delay impacts on project completion
- Supporting extension of time (EOT) claims
- Optimizing resource allocation on critical activities
How to Use This Calculator
Define Activities
Enter activity names, durations and predecessors. Links are finish-to-start with no lags.
Build Network
The calculator creates the activity network and calculates early/late dates.
Identify Critical Path
View the longest path through the network that determines project duration.
Review Float Analysis
See early and late dates and total float for each activity to understand scheduling flexibility.
Typical Scenarios in UAE & Gulf Projects
A planner checks a summary network in days: piling 60, raft 45, typical floors 360, then MEP rough-in 300, façade 240 and interior fit-out 200 in parallel, then testing and commissioning 60. The calculator gives 825 days with the critical path Piling → Raft → Typical floors → MEP rough-in → Testing and commissioning. Façade has 60 days of total float and fit-out 100 days.
A variation adds 45 days to MEP rough-in, which is critical: the calculator shows the project moving from 825 to 870 days, a 45-day delay. The same 45 days added to interior fit-out, which has 100 days of float, leaves the end date at 825 days. This supports a time-impact discussion under the contract's extension of time clause (FIDIC 1999 Red Book Sub-Clause 8.4; 8.5 in the 2017 edition); concurrency and a full delay analysis are outside this tool.
Frequently Asked Questions
Take Your Calculations Further
This calculator reflects the logic built into Arkan's construction management platform.
Last Updated: January 2026
Standards Reference: Critical Path Method (forward and backward pass), PMBOK Schedule Management