S-Curve Generator

Generate project S-curves for cash flow and progress planning. Supports early start, late start, and bell curve distributions with interactive charts and data export.

Project Parameters

AED 50,000,000

Standard S-curve with peak in middle

Monthly Cash Flow
MonthMonthlyCumulative%
Month 1AED 961,988AED 961,9881.9%
Month 22.1M3.1M6.1%
Month 33.9M6.9M13.8%
Month 46.0M12.9M25.8%
Month 57.7M20.6M41.2%
Month 68.4M29.0M58.1%
Month 77.7M36.8M73.5%
Month 86.0M42.7M85.4%
Month 93.9M46.6M93.1%
Month 102.1M48.7M97.3%
Month 11AED 961,98849.6M99.3%
Month 12AED 370,23650.0M100.0%
Distribution Types

Early Start (Front-loaded)

Higher mobilization costs, faster ramp-up

Late Start (Back-loaded)

Delayed mobilization, back-loaded finishing works

Linear

Constant rate of expenditure throughout project

Bell Curve (Standard S)

Typical construction profile with peak at midpoint

Duration

12

Total Value

50.0M

Peak Month

Month 6

S-Curve (Cumulative Progress)

Cumulative planned value over project duration

Monthly Cash Flow

Planned monthly expenditure

Combined View
Key Statistics

Average Monthly

4.2M

Peak Monthly Value

8.4M

50% Progress At

Month 6

Final Value

50.0M

Notes:

  • S-curve represents planned value baseline
  • Compare actual progress against this curve for variance analysis
  • Early/Late start affects cash flow timing
  • Bell curve is typical for standard construction projects
  • Use for earned value management (EVM) baseline
Save Your Calculation
Get a professional PDF report of this calculation, plus access to templates and additional resources.

REFERENCE INFORMATION

This tool provides standard reference data compiled from industry sources.

Note:

• Data is provided for quick reference and may not reflect the most current standards or specifications.

Need More Than Calculators?

Arkan brings all your construction management together: BOQ tracking, payment certificates, document management, scheduling, and more. All integrated. All in one place.